Case Studies
Manufacturing Metal Bars
and Tubes Through a Furnace
Overview
Metal processing plants are continually
seeking methods of refining their production and scheduling
techniques in order to remain
competitive in today’s market. Visual8 has developed an
Adaptive Planning and Scheduling system for a manufacturing facility
that processes metal pieces through a series of furnaces that
enables it to excel within the industry.
The Challenge: Balancing Performance Criteria
Furnace treatment requires schedulers to balance several potentially
conflicting priorities. These include meeting client due dates,
optimizing furnace efficiency, and minimizing piece delays and
overall cost. For one metal treatment plant, the tension of maintaining
equilibrium between due dates and efficiency has always posed
a problem.
Due Dates
In order to meet customer demands, the scheduler forced a less
efficient furnace lineup for a short period of time. However,
inefficient furnace usage ultimately resulted in greater delay
times between products in the long term; attempts to meet customers’ requirements
one week were detrimental to meeting those needs for subsequent
weeks.
Efficiency
Generating an efficient schedule was also a challenge. Pieces
are processed through a series of furnaces, but an optimal
sequence through one furnace is not necessarily optimal through
another. Even the definition for “efficient” was
a debatable issue. Is an efficient system one in which the
delays between pieces are minimized? Or, is an efficient system
one in which the heating and cooling curves of the furnaces
are as smooth as possible?
Planning was performed by a single scheduler using simple intuition
with no forward-view of when pieces might be completed, and the
process provided little flexibility to adapt to unforeseen situations.
Obtaining acceptable sequences was a manually-intensive process
that could not be easily modified because the plant lacked the
manpower. As a result, the plant was consistently behind schedule
and attempted to make up for this by dictating inefficient lineups
that appeased customers in the short term.
A more flexible, timely, and integrated scheduling
method was required in order to better manage the metal treatment
process.
The SIMUL8-Planner Solution
An on-site assessment
helped to establish the current state of operating conditions
at the facility and revealed a high potential
for success; a SIMUL8-Planner system could easily be linked
to the SQL server database that integrated directly to the Level
2 automation system on the shop floor. This enables the production
data used by SIMUL8-Planner to be updated automatically through
external data links. The results from the sequencing system
could
then be converted to an actual order lineup within the system
as well. A detailed production model was constructed to accurately capture
the flow of material through the furnaces and surrounding equipment.
Routing information and processing times were incorporated into
the model as well as properties specifically developed for this
particular facility; such as information about matching furnace
temperatures and speeds to piece parameters, the delays inherent
in heating and cooling the furnaces between orders, and furnace
speed change delays. All values are alterable using the fully
customizable user interface. Changes made in the system are transferred
back to the SQL system.
Upon completion of the detailed production
model, the SIMUL8-Planner system can be used to quickly evaluate
the performance of different
sequencing rules. The impact of a particular rule can be analyzed
based on the delays incurred between orders, fuel and energy
consumption, and due date conformance. Custom sequencing rules
designed to minimize delays while smoothing the furnace-heating
curve and meeting due dates, and custom reports on Key Performance
Indicators were developed to address the client’s specific
objectives.
 Training, installation, and extended support
were also provided to ensure successful integration of the Adaptive
Planning and
Scheduling system into the daily operations of the plant.
 The
Benefits The SIMUL8-Planner Adaptive Planning
and Scheduling system has transformed this metal furnace plant’s
scheduling process from an inflexible, manually-intensive procedure
into a highly-adaptable,
integrated process.
Easy system downloads provide quick access to the current order
requirements for the facility. Using this information, the SIMUL8-Planner
system generates a feasible order sequence based on the selected
combination of sequencing rules. The scheduler can choose to
download a generated sequence as an actual lineup or to continue
experimenting with different sequencing rules until s/he obtains
the desired Key Performance Indicator values. If an order is
changed or a resource becomes unavailable (a machine breaks down,
for example), the scheduler has the flexibility to rapidly generate
a new schedule.
Using complex scheduling rules for the
furnace system, customized reporting options, complete system
integration, and rapid schedule
generation, the SIMUL8-Planner Adaptive Planning and Scheduling
System has provided this metal manufacturer with responsive scheduling
capability. This allows the scheduler to successfully balance
a range of performance criteria, satisfying both customer expectations
and the plant’s operating constraints.
Contact Us
To learn more about SIMUL8-Planner Adaptive Planning and Scheduling
systems, contact us toll-free at 1-800-878-3373 or by email at
simul8-planner@visual8.com.
|